Construction of a 320,000 SF Pasta Production Facility and Pasta Distribution Center in Avon, NY that will serve the entire East Coast region. This facility is producing over 40,000 lbs. of pasta per day.

M/E Role

Design-Build project. M/E provided complete HVAC, plumbing and electrical design. Systems included: High temperature hot water boiler, 500-ton chiller, two (2) 250 ton chillers, two (2) 100 HP air compressors, R.O. water, food grade package rooftop unit for production area, emergency generator, lighting and power distribution.

Challenges

This was a fast-track design build project. M/E was retained in early July, 2006. Contract documents were released in the middle of September, 2006. The facility was ready for production equipment installation by the end of February, 2007.

Awards

This project received a Merit Award from the Design Build Institute of America for Industrial/Process projects greater than $25M.